Northavon M&E

Client:
Northavon M&E
Location:
Bath Business Park
Date Completed:
1st August 2013

Air Conditioning Ian Hobbs Ian Hobbs Renewables

Specialist Engineers to Water Industry Office move

In 2013, Northavon M&E relocated their offices to a new build in Bath Business Park. Ian Hobbs Technical Services provided the total turnkey solution, with a full mechanical and electrical installation to their newly built industrial unit in the rapid turnaround of 12 weeks.

We handled all of the Internal Design, Planning & Building Regulations for the total package:

  • Mezzanine Floor
  • All partitions (including Fire wall)
  • Dry lining and Suspended ceilings
  • Full decoration of Walls, Floors, Doors, Carpets, Builders Clean
  • Full 3 phase Electrical system with Data, patch panel and all main computer & telephone connections
  • Industrial LED, Office &  Emergency Lighting
  • Full Telephone system
  • CCTV Installation & Integration
  • Door Entry
  • Fire Alarm
  • Mechanical Installation Staff Toilets
  • Canteen welfare facilities
  • Air Conditioning system, Heat Pump, Heat Recovery and Ventilation throughout the building

The total package was delivered in Budget and within the time frame of 12 weeks. The building is now on a iH full facilities maintenance programme.

This is just one example of how Ian Hobbs Technical Services could provide for your business. If you like what you see and think we can help you, get in touch via our contact form.