After successfully tendering for the air conditioning and refrigeration contract, Ian Hobbs Technical Services role in the re-development was to fully manage, install and commission the refrigeration and air conditioning systems for the store. Our approach to energy consumption is simple; reduce consumption across their business units with more efficient equipment.
Our installation team worked alongside the shop fitting company with only 4 weeks to complete the entire store. During this short period of time, we carried out the refurbishment of a cold room, extension a new freezer cold room onto the existing, installed Mitsubishi air conditioning, low energy chiller and freezer cabinets as well as a full installation of heat recovery and ventilation in the staff area and toilets. The store successfully opened on the 20th November 2013 and Ian Hobbs Technical Services are proud to have been a part of the project.